2025 Douglas County, MN Power Outage Report
In 2025, customers in Douglas County, MN went without power for an average of 2.6 hours, a total of 61K customer-hours (Minnesota average 3.7 hours). That ranks 40th worst of 85 Minnesota counties and 2192nd of 3,000 nationally.
Compared with MN, the US and 2024
Coverage line is EAGLE-I's share of Minnesota customers tracked each year.
Biggest outages in Douglas County, 2025
The 10 outage episodes with the most customers out at once. Times are UTC.
| # | Started (UTC) | Ended (UTC) | Duration | Peak out | Customer-hours |
|---|---|---|---|---|---|
| 1 | June 20, 2025 03:30 | June 20, 2025 19:15 | 15h 45m | 8,645 | 21K |
| 2 | November 25, 2025 21:45 | November 26, 2025 09:30 | 11h 45m | 5,204 | 10K |
| 3 | June 2, 2025 19:15 | June 3, 2025 06:30 | 11h 15m | 1,938 | 3,552 |
| 4 | May 1, 2025 16:15 | May 1, 2025 17:15 | 1h | 886 | 750 |
| 5 | October 20, 2025 14:15 | October 20, 2025 18:45 | 4h 30m | 785 | 2,597 |
| 6 | July 23, 2025 15:00 | July 23, 2025 19:00 | 4h | 378 | 999 |
| 7 | December 22, 2025 16:30 | December 22, 2025 20:00 | 3h 30m | 353 | 619 |
| 8 | September 19, 2025 03:45 | September 19, 2025 09:30 | 5h 45m | 339 | 835 |
| 9 | June 23, 2025 12:15 | June 23, 2025 15:45 | 3h 30m | 338 | 281 |
| 10 | April 21, 2025 14:00 | April 21, 2025 18:45 | 4h 45m | 308 | 618 |
Outage episodes by size in 2025: 38 reached 100+ customers, 3 reached 1,000+ customers, 0 reached 10,000+ customers.
Utility reliability filed with the EIA
SAIDI (average outage time per customer) and SAIFI (average interruptions per customer) that utilities serving Douglas County reported on EIA Form 861 for 2025, or their most recent earlier filing. Utility-wide figures, not county-specific.
| Utility | EIA year | SAIDI | SAIFI | SAIDI excl. major events | SAIFI excl. major events |
|---|---|---|---|---|---|
| Otter Tail Power Co | 2024 | 2.6 hrs | 1.37 | 1.9 hrs | 1.09 |
| Northern States Power Co - Minnesota | 2024 | 2.6 hrs | 0.99 | 76 min | 0.80 |
| Lake Region Electric Cooperative - (MN) | 2024 | 5.0 hrs | 1.82 | 1.7 hrs | 1.00 |
| Todd-Wadena Electric Coop | 2018 | 2.4 hrs | 0.70 | 2.4 hrs | 0.68 |
| Runestone Electric Assn | 2024 | 68 min | 0.52 | 52 min | 0.46 |
| Stearns Cooperative Elec Assn | 2024 | 2.2 hrs | 0.82 | 57 min | 0.61 |
| City of Alexandria - (MN) | 2024 | 4 min | 0.09 | 4 min | 0.09 |
About this data
- Outage figures come from DOE/ORNL EAGLE-I, which records customers out by county every 15 minutes. EAGLE-I tracked about n/a of Minnesota's customers in 2025; utilities it does not see are not counted.
- Hours per customer = outage customer-minutes ÷ 23,496 customers (ORNL modeled county customer count), including major storm days. It is comparable across counties but is not the SAIDI a utility files.
- An outage event is a continuous stretch with customers out; counts at 100, 1,000 and 10,000+ use its peak.
- Years loaded: 2015–2025. Douglas County has data for 2015–2025.
Cite this report
MassOutage (massoutage.com), Douglas County, MN annual power outage report, 2025, data as of Oct 3, 2026 02:41 UTC, sources: DOE EAGLE-I (https://eagle-i.doe.gov/); EAGLE-I modeled customer counts (MCC) (https://figshare.com/); EIA Form 861 (utility reliability) (https://www.eia.gov/electricity/data/eia861/). https://massoutage.com/reports/2025/minnesota/douglas-county