PUD No 1 of Grays Harbor County: outages & reliability

As of November 26, 2026 00:55 UTC, no major outages are reported on PUD No 1 of Grays Harbor County's network.

PUD No 1 of Grays Harbor County is an political subdivision utility serving 5 counties in Washington. In 2025, its customers went an average of 17.3 hours without power (SAIDI), across about 2.8 interruptions each. That ranks it #443 of 471 US utilities by reliability, where #1 is the most reliable. Its outage duration is worse than the US average and worse than the Washington median (6.6 h).

Live on its networkLive · county

No major outages currently reported on PUD No 1 of Grays Harbor County's network.

Official reliability

Reported to the US EIA for 2025

Source
17.3 hourswithout power per customer a year (SAIDI)
2.8outages per customer a year (SAIFI)
6.2 hrsaverage outage length (CAIDI)

Worse than the US average (US 4.5 hours). Ranks #443 of 471 US utilities by reliability (#1 = most reliable) · worse than the Washington median (6.6 h).

Residential price

Energy trends
12.7¢ per kWh

Average, US EIA 2025

Average home bill

Bills compared
$132.64 a month

For 1,045 kWh a month, its full-service homes, US EIA 2025.

Smart meters: 0.0% of its meters (2025).

Outage trend · PUD No 1 of Grays Harbor County
0customers out · peak 1
Data as of Nov 26, 2026 00:50 UTC
PUD No 1 of Grays Harbor County: customers without power, last 24 hoursPeak 1 customers out; latest 0 as of Nov 26, 2026 00:50 UTC. Each point is the highest reading in its interval.00.30.50.81Nov 256 AM12 PM6 PM
Use the arrow keys to read values.
Times in EST. Shaded stretches had no reading.

Outage history

How often PUD No 1 of Grays Harbor County customers lose power, for how long, and why.

Reliability over timeOfficial EIA SAIDI, hours without power per customer per year (IEEE, including major events). Over this period PUD No 1 of Grays Harbor County’s reliability has been worsening (lower is better).
PUD No 1 of Grays Harbor County SAIDI by year2018–2025: 2018 4.7h, 2020 4.3h, 2021 8.4h, 2022 14.2h, 2023 4.3h, 2024 7.8h, 2025 17.3h. Highlighted: 2025 (highest).051015204.7h20184.3h20208.4h202114.2h20224.3h20237.8h202417.3h2025
Use the arrow keys to read values.

What causes PUD No 1 of Grays Harbor County outages

Share of outage time by reported cause across the counties it serves (territory-wide, may include other utilities in shared counties).

Outage causes by share of outage-timePlanned / maintenance 49%, Equipment failure 47.2%, Vehicle / accident 3.5%, Trees / vegetation 0.3%Planned / maintenancePlanned / maintenance49%Equipment failureEquipment failure47.2%Vehicle / accidentVehicle / accident3.5%Trees / vegetationTrees / vegetation0.3%
Use the arrow keys to read values.
A reported cause is available for 0.1% of outage-time over 3 months of live data. Shares are of the portion with a known cause; bars are scaled to the largest cause.

Counties served by PUD No 1 of Grays Harbor County (5)

Service territory reported to EIA-861; each links to live outage status and history.

PUD No 1 of Grays Harbor County: FAQ

How reliable is PUD No 1 of Grays Harbor County?
PUD No 1 of Grays Harbor County customers averaged 17.3 hours without power in 2025 (SAIDI), which is frequently affected and worse than the US average, worse than the Washington median (6.6 h), per official US EIA data.
Where does PUD No 1 of Grays Harbor County rank among US electric utilities?
By official EIA SAIDI, PUD No 1 of Grays Harbor County is #443 of 471 US utilities by reliability that report reliability and serve at least three counties, #1 being the most reliable. Overall it is worse than the US average.
How many customers does PUD No 1 of Grays Harbor County serve?
PUD No 1 of Grays Harbor County serves 5 counties across Washington, per its EIA-861 service territory filing.
Where does PUD No 1 of Grays Harbor County provide power?
PUD No 1 of Grays Harbor County operates in Washington. The full list of counties served is below, each linked to its live outage status.

Reliability metrics (SAIDI/SAIFI) and service territory from the US EIA Form 861. SAIDI/SAIFI are IEEE-standard, including major event days. Primary state: Washington; every electric company in Washington.

Data from EIA Form 861 (utility reliability) and DOE/ORNL ODIN, every source we read. Live data as of .